NWC fixes Al-Sharaea overflows in Makkah

The National Water Company (NWC) executed a project for removing overflows in Al-Sharaea 3 residential area, which will serve governmental entities and utilities in the district.

Eng. Awad Al-Qahtani, Makkah General Manager of Water, said that the company has recently developed a complete engineering solution to remove damages and overflows taking place in the Street number 64 in the area. The solution has been approved and is currently under implementation.

Eng. Hasan Al-Qarni, Western Sector General Manager of Projects, said that the project included the execution and connection of network pipelines and attaching the same to the main network. The whole project in addition to the connection operations have been completed in 12 days only. The services are now 100 percent accessible once a customer completes NWC's legal wastewater connection procedures.